1.) 3786.57 - sq.m. - Sub-grade Preparation (Common Material)
2.) 1 - l.s - Construction of Field Office for the Engineer
3.) 1 - l.s - Permits and Clearances
4.) 2 - each - Project Billboard/Signboard
5.) 1 - l.s - Occupational Safety and Health
6.) 1 - l.s - Mobilization/Demobilization
7.) 1 - l.s - Removal of Structures and Obstruction
8.) 656.76 - cu.m - Structure Excavation (Common Soil)
9.) 131.60 - cu.m - Embankment from Roadway/Structure Excavation (Common Soil)
10.) 755.21 - cu.m - Embankment from Borrow (Common Soil)
11.) 154.2 - cu.m - Gravel Fill
12.) 1 - l.s - Softscape
13.) 200 - each - Softscape (Shrubs)
14.) 3,786.57 - sq.m. - Softscape (Grass)
15.) 1 - l.s - Hardscape
16.) 378.66 - cu.m - Garden Soil
17.) 4,472.20 - sq.m. - Paver Blocks
18.) 728 - cu.m - Structural Concrete (Class A, 28 Days)
19.) 223.61 - cu.m - Lean Concrete
20.) 15,405.23 - kg. - Reinforcing Steel (Deformed, Grade 40)
21.) 7,710.20 - kg. - Reinforcing Steel (Deformed, Grade 60)
22.) 1,048.01 - sq.m. - Form works and False works
23.) 3 - each - Catch Basin (CHB)
24.) 1 - l.s - Sewer Line Works
25.) 1 - l.s - Storm Drainage and Downspout
26.) 1 - l.s - Plumbing Fixtures
27.) 1 - l.s - Cold Water Lines
28.) 121.50 - sq.m. - Ceiling (4.5mm thk. Fiber Cement Board-Metal Frame)
29.) 10.44 - m. - Fascia Board (19mm thk., Fiber Cement Board)
30.) 63 - sq.m. - Modular partition
31.) 1 - sq.m. - Aluminum Glass Windows (Sliding Type)
32.) 11.52 - sq.m. - Aluminum Glass Windows (Fixed Type)
33.) 91.30 - sq.m. - Tempered Glass (10mm)
34.) 24.84 - l.m. - Fabricated Metal Roofing Accessory( Gauge 26, 0.551mm thk., Flashing)
35.) 10 - l.m. - Fabricated Metal Roofing Accessory (Gauge 24, 0.701mm thk., Gutters)
36.) 74.20 - sq.m. - Pre-painted Metal Sheets ( above 0.427mm thk., Rib Type, Long Span)
37.) 770.51 - sq.m. - Waterproofing (Cement-base)
Help38.) 435.85 - sq.m. - Glazed Tiles and Trims
39.) 360.35 - sq.m. - Unglazed Tiles
40.) 816.50 - sq.m. - Floor Topping (Plain)
41.) 816.50 - sq.m. - Nonslip Finish
42.) 943.63 - sq.m. - Cement Plaster Finish
43.) 75.60 - sq.m. - Decorative Stone
44.) 976.77 - sq.m. - Painting Works (Masonry/Concrete)
45.) 491.92 - sq.m. - Painting Works (Steel)
46.) 115.30 - l.m. - Polycarbonate Sheets/Panels (Solid)
47.) 579.60 - sq.m. - CHB Non-Load Bearing (including Reinforcing Steel), 100mm thk.
48.) 86 - each - Metal Structure Accessories (Bolts and Rods)
49.) 39.10 - kg. - Metal Structure Accessories (Steel Plates)
50.) 30,635.96 - kg. - Structural Steel (Trusses)
51.) 435.50 - kg. - Structural Steel (Purlins)
52.) 1 - l.s. - Railing
53.) 1 - l.s. - Conduit, Boxes and Fittings (Conduit Works/Conduit Rough-in)
54.) 1 - l.s. - Wires and Wiring Devices
55.) 1 - l.s. - Panel Board with Main & Branch Breakers
56.) 1 - l.s. - Solar Panel with Inverter Battery and Other Devices
57.) 1 - l.s. - Lighting Fixtures
58.) 1 - set - LCD, LED Monitor
59.) 1 - set - Water Tank (Stainless)
60.) 1 - set - Submersible Sump Pump with Control